2003
- In August, Del Mar College sold the first $55 million in bonds
after receiving "Double A" and "Triple A" ratings
from national credit firms.
- College Regents are selecting architectural firms for projects,
and design is proceeding. .
2004 - Design development for the South Campus is underway with construction
scheduled to begin in the spring for full occupancy of that campus in
the fall.
- Infrastructure improvements for West and East Campuses should begin
in the spring.
- Expansions of the Diesel Technology Building and new construction
for Aircraft Technology and Metals Technologies facilities will
begin this year for completion in the summer of 2005.
- Renovation of Richardson Auditorium is scheduled to begin
in late fall.
2005
- Construction on the Health Sciences Facilities, the Public
Safety Training Facility, and the Industrial Education Facilities
will begin in the spring.
- Renovations and remodeling of several existing facilities
are slated for the summer and fall.
- Pedestrian areas and parking improvements on East and West
Campuses will begin this year.
2006
- Fall occupancy is scheduled for the Health Sciences Facilities,
and Public Safety Training Facility.
- Renovations in Garcia Sciences Building will begin late in
the year.
- West Campus Capital Improvements will be substantially completed
by the fall semester.
2007 - Remodeling of the St. Clair Science Building, Gymnasium and Aquatics
Center is scheduled.
- Remaining repair and renovation projects will be completed along with
traffic, parking, and landscape improvements.
- All Capital Improvements slated for this program will be substantially
completed by the spring of 2008.
|